In the full course
What you get
- 400 exam-style questions, each with a full explanation
- 20 performance-based tasks, marked with partial credit
- 200 flashcards, filtered by domain
- The full study guide, 25 chapters
- Timed mock exams matched to the real exam length
- A readiness score weighted by the official exam blueprint
Get full access to PMP - Project Management Professional
All questions, timed exams, flashcards, PDF study guide download & progress tracking.
Lifetime · all courses
$29.99
One payment · future courses included
30 seconds, then straight to checkout.
Pass, or your money back
Reach 85% readiness on this course, sit the real exam, and if you don't pass we refund it in full. Applies to this single-course purchase. Terms.
More free samples
Marked, and passed
Real feedback from people who passed
“I failed my CISSP on the first attempt with another platform. Switched to CertCrush, focused on my weak domains using the tracking feature, and passed three months later. The explanations for wrong answers are genuinely useful, not just 'A is correct because A is correct'.”
“Honestly wasn't expecting much but this is probably the best ten bucks I've spent on exam prep. Did 20–30 questions every morning before work for 6 weeks. Passed with a comfortable margin. The timed exam mode is what really got me comfortable with the pressure.”
“The flashcards are underrated. I used them during my commute and it made a huge difference for the theory-heavy ITIL questions. Passed first try. Already using it again for CISM.”
PMI's senior credential for people who already lead projects. The exam changed on 9 July 2026: 180 questions in 240 minutes, split People 33%, Process 41% and Business Environment 26%, with case-study sets, matching and point-and-click items alongside standard multiple choice. This course is built against that July 2026 Examination Content Outline.
Practice content last updated · Independently written and aligned to PMI’s published exam objectives.
About the PMP - Project Management Professional Exam
The Project Management Professional certification is PMI's senior credential for people who already run projects and want proof of it. The current exam follows the Examination Content Outline published for July 2026, which changed how the questions are shared out. People carries 33%, Process 41%, and Business Environment 26%. That last figure is the one to watch. Under the previous outline Business Environment was worth 8%, so anyone revising from older material walks in having under-prepared about a quarter of the paper. The exam runs 180 questions in 240 minutes, and 10 of those are unscored pretest items that look identical to the rest. PMI widened the item types at the same time. Alongside multiple choice and multiple response you will meet case-study sections where several questions hang off one scenario, matching questions that pair items across columns, graphic-based questions built on a chart, point-and-click items, and pull-down lists. Two 10-minute breaks are built into the sitting, the first of them after the case-study section. Most candidates who struggle are not short on project experience. They answer from how their own employer does things rather than from how PMI frames the situation, and the scenario questions punish that fast. The exam wants a judgement call: what does the project manager do next, given a servant-leadership stance, a delivery approach tailored to the work, and an obligation to the business case. Eligibility runs on education plus months of project leadership, and PMI requires 35 hours of project management training before you apply.
Exam Domains Covered
- People33%
- Process41%
- Business Environment26%
Exam Format & Details
180 questions in 240 minutes, of which 10 are unscored pretest items scattered at random. Item types are case or scenario sets, enhanced matching, graphic-based questions, multiple-choice single response, multiple-response, point and click, matching, and pull-down lists. Matching, point and click and pull-down lists are offered on computer-based testing only. Two 10-minute breaks are built in: the first after the case-study section, the second about midway through the independent questions. Booked through Pearson VUE, either at a test centre or online proctored via OnVUE. PMI publishes no passing score. The PMI Certification Handbook states that the passing score for all PMI exams is set by psychometric analysis against a criterion standard, so the 70% shown here is CertCrush's practice threshold and not a PMI figure. Exam fees vary by PMI membership status and region, and PMI publishes no single USD price.
Why Practice Questions Matter
Practice questions matter more for the PMP than for most exams because almost nothing on it is recall. A question hands you a situation and four defensible-sounding actions, and the work is picking the one PMI considers correct rather than the one your last employer would have chosen. That instinct only shifts through repetition. Working several hundred scenarios teaches you the pattern: talk to the person before escalating, check the agreement before changing the plan, protect the business case before protecting the schedule. It also builds the reading speed you need to clear 180 questions in 240 minutes.
Try 2 performance tasks free
Drag-and-drop, sequencing and configuration tasks that mirror the interactive questions on the real PMP - Project Management Professional exam, marked with partial credit.
Sample Practice Questions
The following questions are a preview of the type of syllabus-aligned questions you will practise in CertCrush. They reflect the format and reasoning style of the PMP - Project Management Professional exam, not actual exam content.
Q1.A utility is choosing between three investment proposals for a metering programme. Proposal A has a net present value of minus 0.3 million and a payback period of two years. Proposal B has a net present value of plus 1.8 million, an internal rate of return of 12% and a payback period of five years. Proposal C has a net present value of plus 0.6 million, an internal rate of return of 8% and a payback period of four years. Which proposal should the project manager recommend?
- A.Proposal B, because its net present value and internal rate of return are both the highest of the viable options.
- B.Proposal A, because the shortest payback period returns the money fastest and reduces exposure.
- C.Proposal C, because it balances a positive net present value against a shorter payback than Proposal B.
- D.Proposal A, combined with Proposal C, because together they recover the investment sooner than Proposal B alone.
Domain: Process
Q2.A predictive rail signalling project runs in four phases with a gate at the end of each one. The project manager wants confidence that the agreed end state is still the one the organisation wants. When should the vision and its success criteria be re-confirmed?
- A.At each phase gate, alongside the go or no-go decision.
- B.Only at closure, when the benefits are measured.
- C.Only if a stakeholder raises a concern about the direction of the project.
- D.Monthly, at the same time the cost report is produced.
Domain: People
Q3.A predictive records digitisation project has been forecasting a breach of its schedule tolerance for three weeks. The project manager held the news back while the team attempted a recovery, planning to report it at the phase gate in a fortnight if recovery failed. The agreed threshold requires escalation within two working days of a forecast breach. What should the project manager do?
- A.Continue the recovery attempt and report at the gate, since a problem that gets resolved needs no escalation.
- B.Escalate now, setting out the forecast breach, the recovery attempted so far and the options, and accept that the escalation is already late.
- C.Ask the steering committee chair informally whether the phase gate is soon enough.
- D.Include the breach in the next weekly status report rather than using the escalation path.
Domain: Business Environment
Q4.An energy company is consolidating four data centres into one, and the sponsor has said the business case rests on a large reduction in energy consumption that will be reported at handover. Kwame is writing the plan and the old sites are still running today. What should he do?
- A.Capture the current energy consumption of the four sites now as a defined information requirement, before any site is decommissioned.
- B.Estimate the previous consumption at handover from the equipment vendors' published specifications.
- C.Ask the sponsor to remove the energy reduction claim from the business case to avoid a measurement dispute.
- D.Add energy reporting to the closure activities so it is owned by the operations team after handover.
Domain: Process
Q5.Marcus has circulated a document he calls the project management plan for a factory automation project. It contains a Gantt chart, a cost estimate and a list of who is on the team. The sponsor asks whether the plan is complete before the funding gate next week. How should Marcus respond?
- A.It is not complete: it still needs the subsidiary management plans and the approved scope, schedule and cost baselines.
- B.It is complete once the risk register and issue log are attached to it.
- C.It is complete, because a schedule, a budget and a team list are what the sponsor funds.
- D.It is complete for the gate, and the remaining detail can be added after execution starts.
Domain: Process
Q6.A regional bank is replacing its payments platform. The chief financial officer signs the funding, has no appetite for technical detail, and has already asked to be kept out of the weekly discussion. How should the project manager treat her?
- A.Keep her satisfied with a short, decision-focused briefing covering money, dates and the decisions she owns.
- B.Bring her into the weekly working sessions so that nothing affecting the funding is missed.
- C.Send her the full detailed report each week, since she is the person paying for the work.
- D.Monitor her with light-touch updates only, because she asked to be left out of the discussion.
Domain: People
Q7.On a predictive hotel refurbishment, the client's operations manager has been asking the site team for small additions on almost every visit: an extra socket in each room, a wider serving hatch, better lighting in the corridor. None of it has been re-priced and the contractor is now two weeks behind. What should the project manager do?
- A.Stop absorbing the additions, and put each of them through the change process so the time, cost and resource impact is assessed and agreed.
- B.Absorb the smallest items to protect the client relationship and put only the larger ones through the change process.
- C.Escalate the pattern of requests to the sponsor and ask for the operations manager's access to the site team to be restricted.
- D.Record each addition in the issue log and present the accumulated impact at the next monthly review.
Domain: Process
Q8.Marcus is estimating the cable pull on a substation upgrade. Historical records from the same crews give a steady rate of 15 metres of ducting cable an hour, and the design calls for 1,200 metres. What is the BEST estimating approach here, and what does it produce?
- A.Parametric estimating, giving 80 hours.
- B.Analogous estimating, borrowing the cable pull duration from the last substation.
- C.Three-point estimating, because a single measured rate should never be trusted on its own.
- D.Bottom-up estimating, breaking the pull into sections and estimating each separately.
Domain: Process
Q9.During refinement on an adaptive insurance claims product, the product owner has moved an item called "claims document handling" close to the top of the backlog. The team estimates it at roughly three iterations of work and cannot see how to deliver any of it inside one. What should the project manager encourage the team to do?
- A.Split the item during refinement into stories small enough to be delivered and reviewed inside a single iteration.
- B.Raise a change request so that the additional scope of the item is formally approved before work begins.
- C.Extend the length of the next iteration so the item can be completed in one piece.
- D.Move the item back down the backlog until the team has capacity to take all three iterations at once.
Domain: Process
Q10.A project manager on a water treatment upgrade reviews six situations from the past week against the project's governance escalation triggers. Which THREE require escalation? Select THREE.
- A.The forecast schedule variance now breaches the tolerance recorded in the project management plan
- B.The mitigation depends on a decision by the regional grid operator, which sits entirely outside the project's control
- C.A design change proposed by the supplier affects a second project sharing the same substation
- D.A team member asks to swap the order of two tasks scheduled for next week
- E.A defect was found and corrected inside the iteration, within the agreed quality tolerance
- F.The weekly status report went out one working day late
Domain: Business Environment
PMP - Project Management Professional guides & exam news
PMP Practice Questions: 25 Exam-Style Examples With Answers and Explanations (2026 ECO)
Twenty-five PMP exam practice questions written to the Exam Content Outline that took effect on 9 July 2026, weighted across People, Process and Business Environment. Every answer comes with an explanation of why the other options fail.
Is PMP Certification Worth It? A Straight Answer for 2026
The PMP is worth it if you already lead projects in an industry that screens for it. If you are trying to break into project management, the eligibility bar alone rules you out. Here is the honest decision, with PMI's own requirements.
How to Use a PMP Practice Exam (Without Chasing a Score)
A PMP practice exam is a training tool, not a thermometer. Here is how to build one into a study plan, how to review wrong answers properly, and why PMI publishes no passing percentage for you to chase.
PMP Exam Changes 2026: What Actually Changed and How to Study Now
The July 2026 PMP exam rewrote the domain weights, added two new question types and gave you ten more minutes. Here is what changed against the January 2021 outline, and what a candidate should do differently because of it.
Frequently Asked Questions
Does the PMP - Project Management Professional course include performance-based questions?
Yes. The PMP - Project Management Professional course includes 20 performance-based questions (PBQs): hands-on tasks that mirror the interactive questions on the real exam, including drag-and-drop matching, sequencing and configuration screens. Each one is marked with partial credit, so you can see exactly which placements were wrong, and every task includes a full explanation. The first two are free to try.
What is included in the free PMP - Project Management Professional sample?
The free sample includes 10 syllabus-aligned practice questions, sample flashcards, and a preview chapter from the study guide. No account or payment is required to try the sample.
How many questions are in the full PMP - Project Management Professional course?
The full PMP - Project Management Professional course includes 400 practice questions and 20 performance-based tasks, covering all 3 exam domains. Every question carries a full explanation for the right answer and the wrong ones.
Are these official PMI exam questions?
No. CertCrush questions are independently written and syllabus-aligned. They mirror the format, difficulty, and reasoning style of the official exam. We are not affiliated with or endorsed by PMI.
Which domains does the PMP - Project Management Professional course cover?
The course covers 3 exam domains: People, Process, Business Environment.
Can I study on mobile?
Yes. CertCrush is fully responsive and works on phones, tablets, and desktops. The timed exam, flashcards, and study guide all work on mobile without installing an app.
What happens when I create an account?
Creating a free account lets you access full courses, track your weak areas by domain, and resume practice sessions across devices. No credit card is required to register.
Start with 10 free questions
No account, no card. The full PMP - Project Management Professional course is $9.99, once.