Free PRINCE2 Practitioner Practice Questions

The PRINCE2 Practitioner exam is up to 70 questions in 150 minutes. CertCrush provides 400 syllabus-aligned practice questions across all 4 exam domains, each with a full explanation. Free to try, no account required.

No account · No card · Pass or refund

Try one · Principles

A Louistown City Council Project Manager wants lessons from the council's previous community projects to shape the new project from its very first activities. In which process should these previous lessons first be captured?

Practice questions
400
Exam time limit
150 min
Practice pass mark
60%

In the full course

What you get

  • 400 exam-style questions, each with a full explanation
  • 200 flashcards, filtered by domain
  • The full study guide, 19 chapters
  • Timed mock exams matched to the real exam length
  • A readiness score weighted by the official exam blueprint

Get full access to PRINCE2 Practitioner

All questions, timed exams, flashcards, PDF study guide download & progress tracking.

This course

$9.99

one-time

Pass or refund
Create account and buy

30 seconds, then straight to checkout.

Black Friday · until 30 November

Lifetime · all courses

$29.99$19.99

One payment · future courses included

Create account and buy

30 seconds, then straight to checkout.

PASS GUARANTEEOR MONEY BACK

Pass, or your money back

Reach 85% readiness on this course, sit the real exam, and if you don't pass we refund it in full. Applies to this single-course purchase. Terms.

More free samples

Marked, and passed

Real feedback from people who passed

“The flashcards are underrated. I used them during my commute and it made a huge difference for the theory-heavy ITIL questions. Passed first try. Already using it again for CISM.”
JRJames R.ITIL 5 Foundation
“I failed my CISSP on the first attempt with another platform. Switched to CertCrush, focused on my weak domains using the tracking feature, and passed three months later. The explanations for wrong answers are genuinely useful, not just 'A is correct because A is correct'.”
MTMarcus T.ISC² CISSP
“Honestly wasn't expecting much but this is probably the best ten bucks I've spent on exam prep. Did 20–30 questions every morning before work for 6 weeks. Passed with a comfortable margin. The timed exam mode is what really got me comfortable with the pressure.”
PSPriya S.CompTIA Security+

Scenario-based practice for the PRINCE2 7 Practitioner exam. Questions, flashcards and a study guide built around applying and tailoring the seven principles, the people element, the seven practices and the seven processes.

Practice content last updated · Independently written and aligned to PeopleCert’s published exam objectives.

About the PRINCE2 Practitioner Exam

The PRINCE2 7 Practitioner exam does not ask what a highlight report is. It hands you a project scenario, describes what the project manager or the board has just done, and asks whether that was right and why. Most candidates who fail know the definitions. They lose marks on the reason: they pick Yes when the action was correct, then choose the wrong justification. This course is built for that problem. It covers the four areas PeopleCert tests: principles applied in context, the people element that was added in version 7, the seven practices (Business Case, Organizing, Plans, Quality, Risk, Issues and Progress) and the seven processes from Starting Up a Project to Closing a Project. Practices carry 51 percent of the marks, so they get the most questions here too. You get scenario questions in the style of the real paper, flashcards for the terms that version 7 renamed or introduced, and a study guide you can filter by area. Each explanation says why the right answer is right and why the tempting wrong one fails, because that is the judgement the exam rewards. The course suits anyone holding a PRINCE2 Foundation certificate, in version 6 or version 7, who now needs to apply the method rather than recite it. If you studied version 6, watch for the new words: management approaches instead of strategies, practices instead of themes, and a project initiation documentation that now carries sustainability and the benefits management approach.

Exam Domains Covered

  • Principles10%
  • People9%
  • Practices51%
  • Processes30%

Exam Format & Details

70 marks across 56 questions and sub-questions, 150 minutes, open book (the official PRINCE2 7 manual only). Pass mark 60 percent, which is 42 marks. Every question refers to a project scenario booklet. Classic questions have four options and are worth one mark; matching questions ask you to match three items to a list of five or six options and are worth up to three marks. No negative marking. Candidates sitting in a second language can get 25 percent extra time. Booked through PeopleCert, online or at an accredited training organisation. Requires a PRINCE2 Foundation (version 6 or 7) or another eligible qualification.

Why Practice Questions Matter

The exam is open book, so knowing where a fact sits in the manual is not the hard part. Telling apart three answers that all sound sensible is. Practice questions train that judgement: you read a short scenario, decide which practice or process it is testing, and check your reasoning against the explanation. Doing this many times teaches you the patterns the distractors follow, such as the project manager taking a decision that belongs to the board, or a strategy term from version 6 slipped into an option. Timed practice also matters, because 150 minutes for 70 marks leaves little room to read the booklet twice.

Sample Practice Questions

The following questions are a preview of the type of syllabus-aligned questions you will practise in CertCrush. They reflect the format and reasoning style of the PRINCE2 Practitioner exam, not actual exam content.

Q1.The Louistown project board approves a request for change to a baselined product. Which TWO actions should the project manager then take? (Choose TWO.)

  • A.Update the baseline and configuration records once the change is implemented
  • B.Close the related risk register entries, since approved changes carry no new risk
  • C.Create a second issue report to track the work needed to implement the change
  • D.Update the issue register and the issue report to record the board's decision
  • E.Raise an exception report because the approved change alters the project baseline

Domain: Practices

Q2.A Louistown City Council Project Manager wants lessons from the council's previous community projects to shape the new project from its very first activities. In which process should these previous lessons first be captured?

  • A.Starting up a Project
  • B.Initiating a Project
  • C.Managing a Stage Boundary
  • D.Controlling a Stage

Domain: Principles

Q3.The Louistown project board wants to avoid becoming a bottleneck for routine change decisions. Which TWO statements about delegating change authority are correct? (Choose TWO.)

  • A.The change authority sets its own limits once the board has appointed it to the role
  • B.The change authority also decides when a stage is forecast to exceed its tolerances
  • C.It can be held by an individual, a group, or the project manager for minor changes
  • D.Its decisions are funded from the stage budget rather than from a separate budget
  • E.The delegation must state exactly what can be decided and up to what financial limit

Domain: Practices

Q4.A NowByou project plan lists every product in detail but says nothing about the outcomes or benefits those products will enable. The executive is concerned. Which PRINCE2 7 planning emphasis has been overlooked?

  • A.Plans should be produced in full detail for all stages, so the benefits review can start in initiation
  • B.Plans should consider the outcomes and benefits the products enable, linking plans to the business case
  • C.Plans should list activities before products, so that the benefits of each activity can be traced
  • D.Plans should leave benefits to the benefits management approach and focus only on specialist products

Domain: Practices

Q5.The project manager is drafting the issue management approach for the Louistown project. Which TWO items belong in it? (Choose TWO.)

  • A.The limits within which the change authority may approve requests for change
  • B.The impact analysis prepared for the request to add a citizen feedback portal
  • C.The current list of open issues with their priority, severity and present status
  • D.The board's recorded decision on the off-specification raised in the last stage
  • E.Thresholds for when an issue report is needed rather than only a register entry

Domain: Practices

Q6.NowByou is in week six of an eight-week stage. The project manager reviews checkpoint reports and forecasts that the stage will finish two weeks late. The stage has one week of time tolerance. Which action should the project manager take?

  • A.Report the delay in the end stage report so the board sees the whole stage in one place
  • B.Ask team managers to recover the time by reallocating work, without informing the board
  • C.Escalate the delay directly to corporate management, as the delivery date is at risk
  • D.Raise an exception report to the project board now, with options and a recommendation

Domain: Practices

Q7.A three-year Louistown City Council project has stable, nine-month stages. The board proposes dropping highlight reports altogether and relying on end stage reports, to reduce reporting effort. Is this appropriate tailoring?

  • A.No, because the board would have no regular update between boundaries; reducing frequency would be better
  • B.Yes, because end stage reports give the board all of the progress information it needs on a long, stable project
  • C.Yes, because highlight reports are optional when stages are longer than six months and risk is low
  • D.No, because highlight reports must be produced weekly whatever the length or risk of the project

Domain: Practices

Q8.A NowByou project uses a Kanban board that all stakeholders can see. The project manager stops producing highlight reports, saying the project board can view the Kanban board whenever it likes. Is this appropriate?

  • A.Yes, because tailoring allows any process to be adapted to suit the delivery environment
  • B.Yes, because a Kanban board gives more timely information than any periodic report
  • C.No, because the board must still receive progress reports, although their format can change
  • D.No, because Kanban boards are not a recognised reporting tool in PRINCE2 projects

Domain: Processes

Q9.Louistown City Council is starting a project to replace its citizen services portal. The project board has an executive and a senior supplier but no senior user, because the council believes the executive can speak for citizens. What should the project manager recommend?

  • A.Represent the user interest personally, since the project manager serves all three project interests
  • B.Appoint a senior user from the council's service delivery team to represent the user interest
  • C.Ask the senior supplier to also represent users, as the supplier designs the portal they will use
  • D.Accept the board as it is, because the executive has overall authority over every project interest

Domain: Practices

Q10.A Data Knowledge project manager presents a document to the project board that lists each user request to alter delivered products, with impact analysis and approval status, and calls it the change management approach. Which statement is correct?

  • A.It should be merged into the change management approach so that a single product covers all project change
  • B.It describes change control under the Issues practice, so it is not the change management approach
  • C.It is a valid change management approach, because it records how changes requested by users are handled
  • D.It is the communication management approach, because it records the requests received from stakeholders

Domain: People

PRINCE2 Practitioner guides & exam news

Frequently Asked Questions

What is included in the free PRINCE2 Practitioner sample?

The free sample includes 10 syllabus-aligned practice questions, sample flashcards, and a preview chapter from the study guide. No account or payment is required to try the sample.

How many questions are in the full PRINCE2 Practitioner course?

The full PRINCE2 Practitioner course includes 400 practice questions, covering all 4 exam domains. Every question carries a full explanation for the right answer and the wrong ones.

Are these official PeopleCert exam questions?

No. CertCrush questions are independently written and syllabus-aligned. They mirror the format, difficulty, and reasoning style of the official exam. We are not affiliated with or endorsed by PeopleCert.

Which domains does the PRINCE2 Practitioner course cover?

The course covers 4 exam domains: Principles, People, Practices, Processes.

Can I study on mobile?

Yes. CertCrush is fully responsive and works on phones, tablets, and desktops. The timed exam, flashcards, and study guide all work on mobile without installing an app.

What happens when I create an account?

Creating a free account lets you access full courses, track your weak areas by domain, and resume practice sessions across devices. No credit card is required to register.

Start with 10 free questions

No account, no card. The full PRINCE2 Practitioner course is $9.99, once.

Start freeBuy · $9.99